§ 8-2-14. Permit application.  


Latest version.
  • 8-2-14-1 When required. Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, shall first make application to the Building Official and obtain the required permit for the work.

    8-2-14.2 Work authorized. A building, electrical, gas, mechanical or plumbing permit shall carry with it the right to construct or install the work, provided the same are shown on the drawings and set forth in the specifications filed with the application for the permit. Where these are not shown on the drawings and covered by the specifications submitted with the application, separate permits shall be required.

    8-2-14-3 Minor repairs. Ordinary minor repairs may be made with the approval of the Building Official without a permit, provided that such repairs shall not violate any of the provisions of the construction codes.

    8-2-14-4 information required. Each application for a permit, with the required fee, shall be filed with the Building Official on a form furnished for that purpose, and shall contain a general description of the proposed work and its location. The application shall be signed by the owner, or his/her authorized agent. The building permit application shall indicate the proposed occupancy of all parts of the building and of that portion of the site or lot, if any, not covered by the building or structure, and shall contain such other information as may be required by the Building Official.

    8-2-14-5 Time limitations. An application for a permit for any proposed work shall be deemed to have been abandoned six (6) months after the date of filing for the permit, unless before then a permit has been issued. One (1) or more extensions of time for periods of not more than ninety (90) days each may be allowed by the Building Official for the application, provided the extension is requested in writing and justifiable cause is demonstrated.

    8-2-14-6 Work exempt from permit. Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following: